|
|
New ATT Cell Tower |
|
Arrow points to location of the new cell tower from our
picnic spot on
huckleberry hill
Tower location on the "knob" in the background is on Twin
Falls' property
A summer wine and cheese party in the foreground.
L-R Shannon, Margo, Grier and Dave.
View completed tower shot from this
location
|
Tower location ready for some blasting, major regrading
and a big hole to anchor the tower |
Aerial map of Twin Falls with arrow to the new tower
location |
|
Below is a chronological set of
photos showing the progress of the construction of the
new tower
|
|
|
Here's one of the cell radios
Note the huge heat fins
|
|
The crane quickly moves the pieces to the top
|
Cable trays and wiring runs prepared for final
installation |
|
Moving into high gear
Sector antenna mounted to section of galvanized pipe
|
Crane takes it to the top!
The system will cover all three cell phone bands:
700/760Mhz
1900/2100Mhz
850Mhz (5G)
More about cell systems |
Utilities ditch from the power meters to the
equipment shelter.
Conduits contain 220Volt power and the Ziply fiber to downtown.
Red tape is to warn anyone digging in the future that there's a pipe
about to be hit!
|
Techs installing the three sector antenna mounts.
The plan calls for twelve antennas and nine cell radios, all ATT
|
Inside the equipment shelter
Here's the 48 Volt standby battery set on the right.
All the cell radio equipment is at the top of the monopole
...and it all runs on 48 Volts DC
|
Networking equipment on the left inside the equipment
shelter
It's mainly a big "fiber switch".
Fiber to the radios is run up the inside of the
monopole along with a lot of DC power.
A couple of the radios have "dual" fiber ports for the 5G expansion. |
|
Installation of the equipment shelter
Contractor had to get a ground penetrating radar to locate the rebar
just under the concrete. Note the chalklines where the rebar is sunk.
View a shot of the enormous rebar that
was cast into this pad
|
Completed installation of the equipment shelter and
standby generator.
Note the "feet" to put the shelter a foot off the pad. |
10/28 Antenna crew begins installing the antenna
mounts.
That's Duke the lead man for the final install.
Note the galvanized brackets at the base waiting to be hauled up and the
foot pegs leading up into the branches. Cable in upper center is an OSHA
safety device to prevent falls. That big spool is power wire to
run inside the pole to the top |
Climbers had to remove some branches
Sector antenna brackets being bolted to the 150' monopole.
|
|
Two guys and a helper wiring a new dedicated
transformer
|
10/6/21 Complete less radios and antennas |
The County PUD decided they needed a separate
transformer to supply the cell tower.
Here's the 3.8 kV power feeder junction in this vault. New feeder wire
on the LH side ready to be connected.
|
PUD electrician wiring the power co. side of the four meters
Note the 450W Solar Panel array and its control box. This was to power
the fiber transceivers for testing before the county power was available |
Final assembly 9/2/21
Now for the electronics and antennas
|
First section up and crane ready to stack the next section |
Shot looking south as the mobile crane sets up for
the next section
View engineering drawing of 150' monopole
|
Late afternoon work continues
|
Hold-down bolts tightened twice |
Security Fencing installation
|
Looking up from bottom
View wind loading specifications
|
|
Attaching the limbs and lifting one of the sections
to move in place for the crane lift
|
Nice shot down the inside
|
Crate of limbs ready to mount on the tower |
44 Galvanized Bolts, each numbered!
|
Ziply Fiber splice
truck on Jordan road
Connecting the two fiber ends together, one from downtown and one going
up to the tower location |
|
Truck arrives from
Ehresman Engineering in South Dakota
|
Using a couple of heavy machines to maneuver the
section through the gate |
Moving the base gingerly to set it
by the edge of the driveway
|
Second truck arrives a few minutes later |
Middle section pick up and the guys
carefully orchestrate the turn into the driveway |
Getting ready to move everything to the top
|
|
July 7th
Waiting for the Tower to arrive in August
This looks like some kind of an experiment to see if there's any solar
power up here
|
Note the temporary box on a pallet with ~450watts
of panels connected |
Pad Complete 6/14
Ground wires coming across the pad from a perimeter of 2/0 welding
wire |
Some utilities installed and primary power for four
cell providers |
A set of new power panels, all underground power
|
Finished, dried and set |
Taking a photo of the perfectly set ring of anchor
bolts
|
Unbelievable! |
Pour complete! June 11, 2021
|
This was an all-day job!
Note the plastic over the tops of the circle of bolts to make sure they
stay clean |
So much rebar that it had to be tamped down
with a tool from above
|
Welded pieces out the sides and bent over held the
forms together
|
Pumper working its way around the huge form, it took
all day.
We calculated 177 Yds of concrete
|
So many concrete trucks that there had to be a guy at
the bottom with a walkie talkie! |
Ready for the concrete!
|
Stacked 40' pieces all tied together |
This thing is going to be one strong base
|
|
|
Site is really coming together
Rebar will be cross stacked to just below the ring of bolts |
|
Ironworkers preparing to tie in
more rebar |
Circle of bolts will securely hold base of tower
Level shows it "on the money"
|
Hole is dug in middle and site leveled
Forms begin to be installed
|
Two trucks carried 40ft log rebar up the hill |
Forms being positioned.
Estimate is 250 yards of concrete to fill this big box! |
Site is leveled and rough hole is dug in the middle |
Contractor scooping out the rubble and getting set
for the concrete forms |
|
After dynamite charges were set off...
A big pile of rubble |
T
This mammoth loader was used to haul the blast rock
away |
A close look at the pile of rubble reveals all
that is left, primacord that was run to the individual charges.
...More on
primacord
|
Close-up of a blasting cap laying in the rubble |
Individual holes for dynamite after the first
blast
|
|
Here each hole is marked by the explosives technician
for a precision dynamite blast sequence
|
Each hole is readied for a small high explosive
charge and "funnel" to prevent any dust or dirt to fill the bottom
|
Holes needed to be drilled for dynamite charges
Here's a Furukawa 900ES rock
driller
By automatically controlling the impact force, feed force, rotation
force , the drill continuously adapts to
the changing rock conditions, increasing drilling performance and the
life of drill tools |
Looking towards the business end, this is quite a
machine
Rock drilling and blasting company
McCallum rock
|
After the initial leveling of the site |
A series of holes were drilled
Plan was to blast level and then dig another a 10'x10' hole and fill it with
rebar and concrete to serve as a base for the tower and the associated
equipment including a propane powered AC generator
|
Fiber conduit complete: 1.1 miles from top of mountain to Jordan Road
More about
how fiber works |
|
This was quite an undertaking
|
Fiber conduit installed on lower road
Utilities marked. They only hit one waterline. |
Twin Falls residents took advantage of this
unprecedented opportunity to run their own fiber in the ditch. |
Here's Anastasia running a stretch before the
contractors filled it in
View photo of first test sitting next to the
road with a laptop! |
|
The purpose of a
cellular organization |
|
Valhalla Tree Farm
Home
Copyright © 2021 Valhalla Tree Farm. All rights reserved.
11/14/21
|
|