New ATT Cell Tower





Arrow points to location of the new cell tower from our picnic spot on huckleberry hill
Tower location on the "knob" in the background is on Twin Falls' property
A summer wine and cheese party in the foreground.
L-R Shannon, Margo, Grier and Dave.
View completed tower shot from this location

 



Tower location ready for some blasting, major regrading  and a big hole to anchor the tower



Aerial map of Twin Falls with arrow to the new tower location


  
Below is a chronological set of photos showing the progress of the construction of the new tower


   



Here's one of the cell radios
Note the huge heat fins
 



The crane quickly moves the pieces to the top
 



Cable trays and wiring runs prepared for final installation





Moving into high gear
Sector antenna mounted to section of galvanized pipe



Crane takes it to the top!
The system will cover all three cell phone bands:
700/760Mhz
1900/2100Mhz
850Mhz (5G)
More about cell systems







Utilities ditch from the power meters to the equipment shelter.
Conduits contain 220Volt power and the Ziply fiber to downtown.
Red tape is to warn anyone digging in the future that there's a pipe about to be hit!
 




Techs installing the three sector antenna mounts.
The plan calls for twelve antennas and nine cell radios, all ATT

 



Inside the equipment shelter
Here's the 48 Volt standby battery set on the right.
All the cell radio equipment is at the top of the monopole
...and it all runs on 48 Volts DC
 



Networking equipment on the left inside the equipment shelter
It's mainly a big "fiber switch".
Fiber to the radios is run up the inside of the monopole along with a lot of DC power.
A couple of the radios have "dual" fiber ports for the 5G expansion.




Installation of the equipment shelter
Contractor had to get a ground penetrating radar to locate the rebar just under the concrete. Note the chalklines where the rebar is sunk.
View a shot of the enormous rebar that was cast into this pad

 



Completed installation of the equipment shelter and standby generator.
Note the "feet" to put the shelter a foot off the pad.



10/28 Antenna crew begins installing the antenna mounts.
That's Duke the lead man for the final install.
Note the galvanized brackets at the base waiting to be hauled up and the foot pegs leading up into the branches. Cable in upper center is an OSHA safety device to prevent  falls. That big spool is power wire to run inside the pole to the top



Climbers had to remove some branches
Sector antenna brackets being bolted to the 150' monopole.
 




Two guys and a helper wiring a new dedicated transformer
 



10/6/21 Complete less radios and antennas



The County PUD decided they needed a separate transformer to supply the cell tower.
Here's the 3.8 kV power feeder junction in this vault. New feeder wire on the LH side ready to be connected.
 



PUD electrician wiring the power co. side of the four meters
Note the 450W Solar Panel array and its control box. This was to power the fiber transceivers for testing before the county power was available



Final assembly 9/2/21
Now for the electronics and antennas
 



First section up and crane ready to stack the next section



Shot looking south as the mobile crane sets up for the next section
View engineering drawing of 150' monopole
 



Late afternoon work continues
 



Hold-down bolts tightened twice



Security Fencing  installation
 



Looking up from bottom
View wind loading specifications
 




Attaching the limbs and lifting one of the sections to move in place for the crane lift
 



Nice shot down the inside
 



Crate of limbs ready to mount on the tower

44 Galvanized Bolts, each numbered!
 



Ziply Fiber splice truck on Jordan road
Connecting the two fiber ends together, one from downtown and one going up to the tower location


Truck arrives from Ehresman Engineering in South Dakota
 



Using a couple of heavy machines to maneuver the section through the gate

Moving the base gingerly to set it by the edge of the driveway
 



Second truck arrives a few minutes later


 

Middle section pick up and the guys carefully orchestrate the turn into the driveway



Getting ready to move everything to the top
 





July 7th
 Waiting for the Tower to arrive in August
This looks like some kind of an experiment to see if there's any solar power up here
 



Note the  temporary box on a pallet with ~450watts of panels connected



Pad Complete 6/14
Ground wires coming across the pad from a  perimeter of 2/0 welding wire



Some utilities installed and primary power for four cell providers




A set of new power panels, all underground power
 



Finished, dried and set



Taking a photo of the perfectly set ring of anchor bolts
 



Unbelievable!



Pour complete! June 11, 2021
 



This was an all-day job!
Note the plastic over the tops of the circle of bolts to make sure they stay clean



So much rebar that it had to  be tamped down with a tool from above
 



Welded pieces out the sides and bent over held the forms together
 



Pumper working its way around the huge form, it took all day.
We calculated 177 Yds of concrete
 



So many concrete trucks that there had to be a guy at the bottom with a walkie talkie!



Ready for the concrete!
 



Stacked 40' pieces all tied together



This thing is going to be one strong base
 

 



Site is really coming together
Rebar will be cross stacked to just below the ring of bolts


Ironworkers preparing to tie in more rebar



Circle of bolts will securely hold base of tower
Level shows it "on the money"

 



Hole is dug in middle and site leveled
Forms begin to be installed

 



Two trucks carried 40ft log rebar up the hill



Forms being positioned.
Estimate is 250 yards of concrete to fill this big box!



Site is leveled and rough hole is dug in the middle




Contractor scooping out the rubble and getting set for the concrete forms





 

 





After dynamite charges were set off...
A big pile of rubble


T

This mammoth loader was used to haul the blast rock away




 A close look at the pile of rubble reveals all that is left,  primacord that was run to the individual charges. ...More on primacord
 



Close-up of a blasting cap laying in the rubble



Individual holes for  dynamite after the first blast
 





Here each hole is marked by the explosives technician for a precision dynamite blast sequence
 



Each hole is readied for a small high explosive charge and "funnel" to prevent any dust or dirt to fill the bottom

 



Holes needed to be drilled for dynamite charges
Here's a Furukawa 900ES rock driller
By automatically controlling the impact force, feed force, rotation force , the drill continuously adapts to the changing rock conditions, increasing drilling performance and the life of drill tools



Looking towards the business end, this is quite a machine
Rock drilling and blasting company McCallum rock
 



After the initial leveling of the site






A series of holes were drilled
Plan was to blast level and then dig another a 10'x10' hole and fill it with rebar and concrete to serve as a base for the tower and the associated equipment including a propane powered AC generator
 




Fiber conduit complete: 1.1 miles from top of mountain to Jordan Road
More about how fiber works





This was quite an undertaking

 



Fiber conduit installed on lower road
Utilities marked. They only hit one waterline.



Twin Falls residents took advantage of this unprecedented opportunity to run their own fiber in the ditch.



Here's Anastasia running a stretch before the contractors filled it in
 View photo of first test sitting next to the road with a laptop!


The purpose of a cellular organization  
 

Valhalla Tree Farm Home

Copyright © 2021 Valhalla Tree Farm. All rights reserved. 


11/14/21